Construction Planning And Management — Part 1 MCQs with Explanations
Practice high-yield Civil Engineering MCQs on Construction Planning And Management — Part 1 with worked academic solutions for PPSC SDO, FPSC AEE, C&W, Irrigation, NTS.
Questions
40
Difficulty Level
Exam-Level
Target Exams
PPSC SDO, FPSC AEE, C&W...
Estimated Time
48 mins
Exam-Level PPSC SDO FPSC AEE C&W Irrigation NTS
Verified for Commission Syllabus • Oct 14, 2026
40
Verified Practice Questions
Interactive test mode with detailed academic worked solutions
Live Progress|0/40 answered
✓0 correct
✗0 wrong
0% score
🎉 Set complete! All 40 questions answered.
Question 1 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Bar charts are suitable for
Correct Answer: Option A — Minor works
Detailed Academic Explanation:
Bar charts (also called Gantt charts ) are simple graphical schedules used to show the start time, finish time, and duration of different construction activities. They are best suited for minor or small construction works because the number of activities is limited, making the schedule easy to prepare and understand. For large or complex projects , bar charts become difficult to manage since they do not clearly show the relationship or dependency between activities . In such cases, network planning techniques like PERT (Program Evaluation and Review Technique) or CPM (Critical Path Method) are preferred. Easy Trick to Remember: Small Project → Bar Chart Large Project → PERT / CPM Hence, bar charts are most suitable for minor works , making Option A the correct answer.
💡Key Conceptual Anchor:Construction Planning And Management
Question 2 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
Correct Answer: Option D — 4
Detailed Academic Explanation:
This is the correct answer. In construction project management using a bar chart (Gantt chart), each activity is represented by a horizontal bar. The activities mentioned in the question include: 1. Supply of materials for concrete 2. Formwork, reinforcing, and placing of concrete 3. Removal of formwork 4. Curing of concrete Each of these activities requires a separate bar on the chart.
💡Key Conceptual Anchor:Construction Planning And Management
Question 3 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For a given size of bucket, the ideal output of a dragline will be least in
Correct Answer: Option D — Wet sticky clay
Detailed Academic Explanation:
Let's look at each option: Option A: Moist loam: Loam is generally a good soil type for digging, especially when moist. So, output would be relatively good. Option B: Sand and gravel: Sand and gravel are loose materials, easy to dig. Output would be high. Option C: Good common earth: This is also generally good for digging, so output would be decent. Option D: Wet sticky clay: Wet sticky clay is the most difficult material to dig and load. It sticks to the bucket, making it hard to empty and reducing the amount of material that can be moved per cycle. Therefore, the answer is Option D: Wet sticky clay because it offers the least ideal digging conditions, leading to the lowest output.
💡Key Conceptual Anchor:Construction Planning And Management
Question 4 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Works costing less than Rs. 20,000 are treated as
Correct Answer: Option D — Petty works
Detailed Academic Explanation:
In Civil Engineering, works costing less than Rs. 20,000 are typically categorized as Petty works . These are small-scale projects of minor significance that require minimal resources and planning. Therefore, the correct option is D: Petty works .
💡Key Conceptual Anchor:Construction Planning And Management
Question 5 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
Correct Answer: Option A — Rs. 8,43,750
Detailed Academic Explanation:
The double declining balance (DDB) method is an accelerated depreciation method that depreciates the asset faster in the earlier years. The formula for DDB depreciation is: Depreciation for the year = 2 × (1 / useful life) × book value at beginning of year Given: Cost of excavator = Rs. 20,00,000 Estimated life = 8 years Salvage value = Rs. 0 Depreciation rate = 2 × (1 / 8) = 25% Year 1: Depreciation = 25% of 20,00,000 = Rs. 5,00,000 Book value at end of Year 1 = 20,00,000 - 5,00,000 = Rs. 15,00,000 Year 2: Depreciation = 25% of 15,00,000 = Rs. 3,75,000 Book value at end of Year 2 = 15,00,000 - 3,75,000 = Rs. 11,25,000 Year 3: Depreciation = 25% of 11,25,000 = Rs. 2,81,250 Book value at end of Year 3 = 11,25,000 - 2,81,250 = Rs. 8,43,750 Therefore, the correct answer is: Rs. 8,43,750 (Option A).
💡Key Conceptual Anchor:Construction Planning And Management
Question 6 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Power stations are generally treated as
Correct Answer: Option C — Industrial construction
Detailed Academic Explanation:
Power stations are large-scale projects involving the installation of heavy machinery, boilers, turbines, generators, and complex control systems. Such projects require specialized design, skilled manpower, and coordinated construction of structural, mechanical, and electrical components . Because power stations are built to support industrial-level production of energy , they are classified under industrial construction . Light construction generally refers to residential or small commercial buildings, while heavy construction usually relates to infrastructure like dams, highways, and bridges. Electrical construction is only a part of power station work and does not represent the overall project category. Hence, power stations are generally treated as industrial construction , making Option C the correct answer.
💡Key Conceptual Anchor:Construction Planning And Management
Question 7 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The normal time required for the completion of project in the above problem is
Correct Answer: Option C — 14 days
Detailed Academic Explanation:
14 days is the correct answer to “The normal time required for the completion of project in the above problem is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 8 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If t o , t p and t m are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
Correct Answer: Option E — $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$
Detailed Academic Explanation:
$$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$ is the correct answer to “If t o , t p and t m are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 9 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A construction schedule is prepared after collecting
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “A construction schedule is prepared after collecting”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 10 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
Correct Answer: Option C — 3.5 and $$\frac{{25}}{{36}}$$
Detailed Academic Explanation:
3.5 and $$\frac{{25}}{{36}}$$ is the correct answer to “If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 11 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The first stage of a construction, is
Correct Answer: Option C — Initiation of proposal
Detailed Academic Explanation:
Initiation of proposal is the correct answer to “The first stage of a construction, is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 12 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
Correct Answer: Option C — 21 minutes
Detailed Academic Explanation:
21 minutes is the correct answer to “A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 13 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The probability of completion of any activity within its expected time is
Correct Answer: Option A — 50 %
Detailed Academic Explanation:
50 % is the correct answer to “The probability of completion of any activity within its expected time is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 14 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
Correct Answer: Option B — 9 days
Detailed Academic Explanation:
9 days is the correct answer to “For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 15 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For the network shown in the given figure, the expected time for the activity
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “For the network shown in the given figure, the expected time for the activity”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 16 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Time and progress chart of a construction, is also known as
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “Time and progress chart of a construction, is also known as”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 17 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The difference between the time avail-to do a job and the time required to do the job, is known as
Correct Answer: Option B — Float
Detailed Academic Explanation:
Float is the correct answer to “The difference between the time avail-to do a job and the time required to do the job, is known as”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 18 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The Overall in-charge of an organization at the site responsible for the execution of the works, is
Correct Answer: Option B — Engineer
Detailed Academic Explanation:
Engineer is the correct answer to “The Overall in-charge of an organization at the site responsible for the execution of the works, is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 19 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Various activities of a project, are shown on bar charts by
Correct Answer: Option B — Horizontal lines
Detailed Academic Explanation:
Horizontal lines is the correct answer to “Various activities of a project, are shown on bar charts by”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 20 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The main disadvantage of line organization, is
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “The main disadvantage of line organization, is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 21 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The main principle of an organization, is
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “The main principle of an organization, is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 22 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A critical ratio scheduling
Correct Answer: Option D — None of these
Detailed Academic Explanation:
None of these is the correct answer to “A critical ratio scheduling”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 23 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A golden rule for the procurement of construction stones, suggests
Correct Answer: Option B — 67% at the site and 33% under procurement
Detailed Academic Explanation:
67% at the site and 33% under procurement is the correct answer to “A golden rule for the procurement of construction stones, suggests”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 24 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Correct Answer: Option C — $$\frac{{{\text{a}} + 4{\text{m}} + {\text{b}}}}{6}$$
Detailed Academic Explanation:
$$\frac{{{\text{a}} + 4{\text{m}} + {\text{b}}}}{6}$$ is the correct answer to “If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 25 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
Correct Answer: Option C — 40 kg/tonne
Detailed Academic Explanation:
40 kg/tonne is the correct answer to “A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 26 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
Correct Answer: Option A — Reduce by 200 kg
Detailed Academic Explanation:
Reduce by 200 kg is the correct answer to “A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 27 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The time with which direct cost does not reduce with the increase in time is known as
Correct Answer: Option B — Normal time
Detailed Academic Explanation:
Normal time is the correct answer to “The time with which direct cost does not reduce with the increase in time is known as”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 28 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is
Correct Answer: Option C — 900 kg
Detailed Academic Explanation:
900 kg is the correct answer to “If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 29 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Frederick W. Taylor introduced a system of working known as
Correct Answer: Option C — Functional organization
Detailed Academic Explanation:
Functional organization is the correct answer to “Frederick W. Taylor introduced a system of working known as”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 30 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For the execution of a project, a contractor is
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “For the execution of a project, a contractor is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 31 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
Correct Answer: Option A — Rs. 31050
Detailed Academic Explanation:
Rs. 31050 is the correct answer to “An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 32 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
Correct Answer: Option D — 16 days
Detailed Academic Explanation:
16 days is the correct answer to “If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 33 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A dummy activity
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “A dummy activity”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 34 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A Milestone chart
Correct Answer: Option D — None of these
Detailed Academic Explanation:
None of these is the correct answer to “A Milestone chart”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 35 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of
Correct Answer: Option A — 1, 2 and 4
Detailed Academic Explanation:
1, 2 and 4 is the correct answer to “Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 36 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.
Correct Answer: Option B — 1 and 4 are correct
Detailed Academic Explanation:
1 and 4 are correct is the correct answer to “Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 37 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Batching refers to
Correct Answer: Option C — Controlling the quantity of each material into each batch
Detailed Academic Explanation:
Controlling the quantity of each material into each batch is the correct answer to “Batching refers to”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 38 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Military organization is known as
Correct Answer: Option A — Line organization
Detailed Academic Explanation:
Line organization is the correct answer to “Military organization is known as”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 39 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Critical path lies along the activities having total float
Correct Answer: Option C — Zero
Detailed Academic Explanation:
Zero is the correct answer to “Critical path lies along the activities having total float”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 40 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Slack time refers to
Correct Answer: Option B — An event
Detailed Academic Explanation:
An event is the correct answer to “Slack time refers to”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
✓Link copied to clipboard
Continue Your Practice
Airport Engineering — Part 1
Master the next curriculum module with 40 exam-standard MCQs.
In competitive commission exams (FPSC, PPSC, KPPSC, SPSC, CSS, PMS), questions are frequently phrased with distractor options designed to catch rote learners. Whenever you answer an MCQ, read the Detailed Academic Explanation and Conceptual Anchor to understand why the remaining options are incorrect.