Construction Planning And Management — Part 2 MCQs with Explanations
Practice high-yield Civil Engineering MCQs on Construction Planning And Management — Part 2 with worked academic solutions for PPSC SDO, FPSC AEE, C&W, Irrigation, NTS.
Questions
40
Difficulty Level
Exam-Level
Target Exams
PPSC SDO, FPSC AEE, C&W...
Estimated Time
48 mins
Exam-Level PPSC SDO FPSC AEE C&W Irrigation NTS
Verified for Commission Syllabus • Oct 14, 2026
40
Verified Practice Questions
Interactive test mode with detailed academic worked solutions
Live Progress|0/40 answered
✓0 correct
✗0 wrong
0% score
🎉 Set complete! All 40 questions answered.
Question 1 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The most suitable type of equipment for compaction of cohesive soils is
Correct Answer: Option C — Sheep foot rollers
Detailed Academic Explanation:
Sheep foot rollers is the correct answer to “The most suitable type of equipment for compaction of cohesive soils is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 2 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The most popular type of organization used for Civil Engineering Constructions, is
Correct Answer: Option A — Line organization
Detailed Academic Explanation:
Line organization is the correct answer to “The most popular type of organization used for Civil Engineering Constructions, is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 3 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
CPM is
Correct Answer: Option D — All the above
Detailed Academic Explanation:
Option "All the above" is the correct answer for this question under Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 4 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
In time-cost optimization of a project, crashing is done.
Correct Answer: Option D — On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Detailed Academic Explanation:
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope is the correct answer to “In time-cost optimization of a project, crashing is done.”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 5 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Critical path
Correct Answer: Option A — Is always longest
Detailed Academic Explanation:
Is always longest is the correct answer to “Critical path”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 6 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Earliest finish of an activity is always
Correct Answer: Option C — Less than or equal to earliest event time of the following node
Detailed Academic Explanation:
Less than or equal to earliest event time of the following node is the correct answer to “Earliest finish of an activity is always”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 7 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Latest start of an activity is always
Correct Answer: Option A — greater than or equal to latest event time of preceding node
Detailed Academic Explanation:
greater than or equal to latest event time of preceding node is the correct answer to “Latest start of an activity is always”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 8 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively
Correct Answer: Option D — 75 and 83
Detailed Academic Explanation:
75 and 83 is the correct answer to “The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted and pneumatic tyre-mounted machines would be respectively”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 9 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
Correct Answer: Option C — Least cost slope
Detailed Academic Explanation:
Least cost slope is the correct answer to “In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 10 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
Correct Answer: Option B — Rs. 3480
Detailed Academic Explanation:
Rs. 3480 is the correct answer to “A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 11 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel.
Correct Answer: Option B — (i), (ii) and (iv) are correct
Detailed Academic Explanation:
(i), (ii) and (iv) are correct is the correct answer to “Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth. (iv) Output can be increased by increasing the size of shovel.”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 12 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
Correct Answer: Option A — Moist loam
Detailed Academic Explanation:
Moist loam is the correct answer to “For which of the following materials, the output of power shovels for a fixed shovel size will be maximum”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 13 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be
Correct Answer: Option C — Rs. 6,400
Detailed Academic Explanation:
Rs. 6,400 is the correct answer to “The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 14 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Crash project duration is obtained by summing the
Correct Answer: Option D — Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Detailed Academic Explanation:
Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities is the correct answer to “Crash project duration is obtained by summing the”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 15 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Mile Stone charts were invented in the year of
Correct Answer: Option D — 1940
Detailed Academic Explanation:
1940 is the correct answer to “Mile Stone charts were invented in the year of”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 16 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Which one of the following represents an activity?
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “Which one of the following represents an activity”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 17 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct?
Correct Answer: Option D — (i), (ii) and (iii) are correct
Detailed Academic Explanation:
(i), (ii) and (iii) are correct is the correct answer to “The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack which of these statements are correct”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 18 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For excavating utility trenches with precise control of depth, the excavation equipment used is
Correct Answer: Option A — Hoe
Detailed Academic Explanation:
Hoe is the correct answer to “For excavating utility trenches with precise control of depth, the excavation equipment used is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 19 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
Correct Answer: Option B — Loose sand
Detailed Academic Explanation:
Loose sand is the correct answer to “Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 20 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
Correct Answer: Option C — expected time of both activities A and B are same
Detailed Academic Explanation:
expected time of both activities A and B are same is the correct answer to “If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 21 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Which of the following is a weakness of bar chart?
Correct Answer: Option D — All of the above
Detailed Academic Explanation:
All of the above is the correct answer to “Which of the following is a weakness of bar chart”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 22 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For completion of a project, the critical path of the network represents
Correct Answer: Option A — Minimum time
Detailed Academic Explanation:
Minimum time is the correct answer to “For completion of a project, the critical path of the network represents”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 23 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
Correct Answer: Option B — Rs. 5,75,000
Detailed Academic Explanation:
Rs. 5,75,000 is the correct answer to “A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 24 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Which of the following excavators is most suitable for digging under water?
Correct Answer: Option A — Drag line
Detailed Academic Explanation:
Drag line is the correct answer to “Which of the following excavators is most suitable for digging under water”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 25 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions
Correct Answer: Option C — (i) and (iii) are correct
Detailed Academic Explanation:
(i) and (iii) are correct is the correct answer to “Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 26 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Residential buildings are treated as
Correct Answer: Option A — Light construction
Detailed Academic Explanation:
Light construction is the correct answer to “Residential buildings are treated as”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 27 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor
Correct Answer: Option B — (i) and (iv) are correct
Detailed Academic Explanation:
(i) and (iv) are correct is the correct answer to “Output of a bulldozer is (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of the tractor”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 28 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The critical activity has
Correct Answer: Option C — Zero float
Detailed Academic Explanation:
Zero float is the correct answer to “The critical activity has”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 29 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The object of technical planning, is
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “The object of technical planning, is”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 30 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Total float for any activity is defined as the difference between
Correct Answer: Option B — Its latest start time and earliest start time
Detailed Academic Explanation:
Its latest start time and earliest start time is the correct answer to “Total float for any activity is defined as the difference between”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 31 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Interfering float is the difference between
Correct Answer: Option A — Total float and free float
Detailed Academic Explanation:
Total float and free float is the correct answer to “Interfering float is the difference between”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 32 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Free float for any activity is defined as the difference between
Correct Answer: Option A — its earliest finish time and earliest start time for its successor activity
Detailed Academic Explanation:
its earliest finish time and earliest start time for its successor activity is the correct answer to “Free float for any activity is defined as the difference between”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 33 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased.
Correct Answer: Option A — Both A and R is true and R is the correct explanation of A
Detailed Academic Explanation:
Both A and R is true and R is the correct explanation of A is the correct answer to “Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased.”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 34 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float
Correct Answer: Option B — 2 and 3 are correct
Detailed Academic Explanation:
2 and 3 are correct is the correct answer to “Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 35 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Updating may result in
Correct Answer: Option D — All of the above
Detailed Academic Explanation:
All of the above is the correct answer to “Updating may result in”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 36 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The first method invented for planning projects, was
Correct Answer: Option A — Bar chart method
Detailed Academic Explanation:
Bar chart method is the correct answer to “The first method invented for planning projects, was”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 37 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A contractor has two options; (l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he
Correct Answer: Option A — Should invest in neither of the two projects
Detailed Academic Explanation:
Should invest in neither of the two projects is the correct answer to “A contractor has two options; (l) : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 38 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Free float is mainly used to
Correct Answer: Option B — Identify the activities, which can be delayed without affecting the total float of succeeding activity
Detailed Academic Explanation:
Identify the activities, which can be delayed without affecting the total float of succeeding activity is the correct answer to “Free float is mainly used to”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 39 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
Correct Answer: Option D — Independent float
Detailed Academic Explanation:
Independent float is the correct answer to “The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
Question 40 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Preliminary project report for a road project must contain
Correct Answer: Option C — The soil survey, traffic survey, concept design and approximate cost
Detailed Academic Explanation:
The soil survey, traffic survey, concept design and approximate cost is the correct answer to “Preliminary project report for a road project must contain”. This question is standard in competitive examination syllabi for Construction Planning And Management.
💡Key Conceptual Anchor:Construction Planning And Management
✓Link copied to clipboard
Continue Your Practice
Airport Engineering — Part 1
Master the next curriculum module with 40 exam-standard MCQs.
In competitive commission exams (FPSC, PPSC, KPPSC, SPSC, CSS, PMS), questions are frequently phrased with distractor options designed to catch rote learners. Whenever you answer an MCQ, read the Detailed Academic Explanation and Conceptual Anchor to understand why the remaining options are incorrect.