Estimating And Costing — Part 1 MCQs with Explanations

Practice high-yield Civil Engineering MCQs on Estimating And Costing — Part 1 with worked academic solutions for PPSC SDO, FPSC AEE, C&W, Irrigation, NTS.

Questions
40
Difficulty Level
Exam-Level
Target Exams
PPSC SDO, FPSC AEE, C&W...
Estimated Time
48 mins
Exam-Level PPSC SDO FPSC AEE C&W Irrigation NTS
Verified for Commission Syllabus • Oct 14, 2026
40

Verified Practice Questions

Interactive test mode with detailed academic worked solutions

Live Progress | 0/40 answered
✓ 0 correct ✗ 0 wrong 0% score
Question 1 of 40
★ PPSC SDO ★ FPSC AEE

A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is

Question 2 of 40
★ PPSC SDO ★ FPSC AEE

The main factor to be considered while preparing a detailed estimate, is

Question 3 of 40
★ PPSC SDO ★ FPSC AEE

Berms are provided in canals if these are

Question 4 of 40
★ PPSC SDO ★ FPSC AEE

If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by

Question 5 of 40
★ PPSC SDO ★ FPSC AEE

Size, capacity and materials need be specified for

Question 6 of 40
★ PPSC SDO ★ FPSC AEE

The expected out turn of 12 mm plastering with cement mortar is

Question 7 of 40
★ PPSC SDO ★ FPSC AEE

The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

Question 8 of 40
★ PPSC SDO ★ FPSC AEE

If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is

Question 9 of 40
★ PPSC SDO ★ FPSC AEE

The rate of payment is made for 100 cu m (per % cu m) in case of

Question 10 of 40
★ PPSC SDO ★ FPSC AEE

Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds

Question 11 of 40
★ PPSC SDO ★ FPSC AEE

The value of 'A' of Indian type W.C. shown in the given figure is:

Question 12 of 40
★ PPSC SDO ★ FPSC AEE

The value of 'C' of Indian type W.C. shown in the given figure is:

Question 13 of 40
★ PPSC SDO ★ FPSC AEE

The value of 'B' of Indian type W.C. shown in the given figure is:

Question 14 of 40
★ PPSC SDO ★ FPSC AEE

The area of the cross-section of a road fully in banking shown in the given figure, is

Question 15 of 40
★ PPSC SDO ★ FPSC AEE

The concrete work for the following part of the building of specified thickness is measured in square meters

Question 16 of 40
★ PPSC SDO ★ FPSC AEE

The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

Question 17 of 40
★ PPSC SDO ★ FPSC AEE

The expected out turn of half brick partition wall per mason per day is

Question 18 of 40
★ PPSC SDO ★ FPSC AEE

The measurement is made in square metre in case of

Question 19 of 40
★ PPSC SDO ★ FPSC AEE

The measurement is made for stone work in square metre in case of

Question 20 of 40
★ PPSC SDO ★ FPSC AEE

As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken

Question 21 of 40
★ PPSC SDO ★ FPSC AEE

Pick up the correct statement in case of water supply.

Question 22 of 40
★ PPSC SDO ★ FPSC AEE

The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is

Question 23 of 40
★ PPSC SDO ★ FPSC AEE

For the construction of buildings, the subheads of the estimate are

Question 24 of 40
★ PPSC SDO ★ FPSC AEE

The damp proof course (D.P.C.) is measured in

Question 25 of 40
★ PPSC SDO ★ FPSC AEE

The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

Question 26 of 40
★ PPSC SDO ★ FPSC AEE

The area of a sloping surface of a protective embankment of mean height ‘d’, side slopes S : 1 and length ‘L’ is

Question 27 of 40
★ PPSC SDO ★ FPSC AEE

The detention period in a septic tank is assumed

Question 28 of 40
★ PPSC SDO ★ FPSC AEE

Carpet area does not include the area of

Question 29 of 40
★ PPSC SDO ★ FPSC AEE

While estimating the qualities for the construction of a building, the correct metric unit is

Question 30 of 40
★ PPSC SDO ★ FPSC AEE

The volume is measured correct to the nearest

Question 31 of 40
★ PPSC SDO ★ FPSC AEE

The area is measured correct to the nearest

Question 32 of 40
★ PPSC SDO ★ FPSC AEE

While preparing a detailed estimate

Question 33 of 40
★ PPSC SDO ★ FPSC AEE

The plinth area of a building not includes

Question 34 of 40
★ PPSC SDO ★ FPSC AEE

In the mid-section formula

Question 35 of 40
★ PPSC SDO ★ FPSC AEE

The inspection pit or chamber is a manhole provided in a base drainage system

Question 36 of 40
★ PPSC SDO ★ FPSC AEE

The cross-sectional area of the embankment of a canal fully in embankment in the given figure is

Question 37 of 40
★ PPSC SDO ★ FPSC AEE

Anti-siphonage pipe is connected to

Question 38 of 40
★ PPSC SDO ★ FPSC AEE

The 'centre line method' is specially adopted for estimating

Question 39 of 40
★ PPSC SDO ★ FPSC AEE

In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and

Question 40 of 40
★ PPSC SDO ★ FPSC AEE

According to ISI method of measurement, the order of the sequence is

✓ Link copied to clipboard
Continue Your Practice

Airport Engineering — Part 1

Master the next curriculum module with 40 exam-standard MCQs.

Next Practice Set →

💡 Examiner's Advisory for Civil Engineering

In competitive commission exams (FPSC, PPSC, KPPSC, SPSC, CSS, PMS), questions are frequently phrased with distractor options designed to catch rote learners. Whenever you answer an MCQ, read the Detailed Academic Explanation and Conceptual Anchor to understand why the remaining options are incorrect.

More Modules in Civil Engineering

View All →
📚

Study Guides

Topic summaries and syllabus breakdown

Explore Guides →
🎯

Complete Library

Search through 78,000+ verified MCQs

Browse Library →
📱

Mobile App

Offline mock tests and instant bookmarks

Get Mobile App →