Irrigation Engineering — Part 1 MCQs with Explanations
Practice high-yield Civil Engineering MCQs on Irrigation Engineering — Part 1 with worked academic solutions for PPSC SDO, FPSC AEE, C&W, Irrigation, NTS.
Questions
40
Difficulty Level
Exam-Level
Target Exams
PPSC SDO, FPSC AEE, C&W...
Estimated Time
48 mins
Exam-Level PPSC SDO FPSC AEE C&W Irrigation NTS
Verified for Commission Syllabus • Oct 14, 2026
40
Verified Practice Questions
Interactive test mode with detailed academic worked solutions
Live Progress|0/40 answered
✓0 correct
✗0 wrong
0% score
🎉 Set complete! All 40 questions answered.
Question 1 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Irrigation water having the concentration of Na ++ , Ca ++ and Mg ++ as 20, 3 and 1 Milli equivalent per litre respectively will be classified as
Correct Answer: Option D — Very high sodium water
Detailed Academic Explanation:
Irrigation water is classified based on its sodium concentration relative to the concentrations of calcium and magnesium ions. The classification is determined by the sodium absorption ratio (SAR), which is calculated using the following formula: SAR = (Na ++ / √(Ca ++ + Mg ++ )) * 100 Given the concentrations provided: Na ++ = 20 meq/L Ca ++ = 3 meq/L Mg ++ = 1 meq/L Plugging these values into the SAR formula: SAR = (20 / √(3 + 1)) * 100 SAR ≈ (20 / √4) * 100 SAR ≈ (20 / 2) * 100 SAR ≈ 10 * 100 SAR ≈ 1000 According to the classification: SAR < 10: Low sodium water 10 ≤ SAR < 18: Medium sodium water 18 ≤ SAR < 26: High sodium water SAR ≥ 26: Very high sodium water Since the calculated SAR is approximately 100, the irrigation water falls into the category of very high sodium water .
💡Key Conceptual Anchor:Irrigation Engineering
Question 2 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The difference in level between the top of a bank and supply level in a canal, is called
Correct Answer: Option B — Free board
Detailed Academic Explanation:
In irrigation engineering, the difference in level between the top of a bank and the supply level in a canal is termed as the free board . This term refers to the vertical distance between the water level in the canal and the top of the embankment or bank. The free board provides a safety margin to prevent overflow or breach of the canal embankment during high water flow or flooding events.
💡Key Conceptual Anchor:Irrigation Engineering
Question 3 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The state of the soil when plants fail to extract sufficient water for their requirements, is
Correct Answer: Option B — Permanent wilting point
Detailed Academic Explanation:
The correct answer is Permanent wilting point . In irrigation engineering , the term Permanent wilting point refers to the state of the soil when plants are unable to extract sufficient water for their needs. At this point, the soil moisture content is so low that plants wilt permanently, even if moisture is added to the soil. So, the sentence should read: "The state of the soil when plants fail to extract sufficient water for their requirements, is Permanent wilting point ."
💡Key Conceptual Anchor:Irrigation Engineering
Question 4 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A 6 hours storm had 4 cm of rainfall and the resulting runoff was 2 cm. If ϕ index remains at the same value, the runoff due to 10 cm of rainfall in 12 hours in the catchment is
Correct Answer: Option B — 6.0 cm
Detailed Academic Explanation:
Infiltration Rate =2/6=1/3cm/hr Infiltration=1/3*12=4cm Run-off= 10-4=6 cm
💡Key Conceptual Anchor:Irrigation Engineering
Question 5 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The main function of a divide wall is to
Correct Answer: Option C — separate the undersluices from weir proper
Detailed Academic Explanation:
The main function of a divide wall is to separate the undersluices from the weir proper and provide a smooth flow of water by guiding it efficiently. It helps in: - Preventing crosscurrents and turbulence that may interfere with the proper functioning of the undersluices. - Controlling sedimentation by ensuring that silt-laden water flows towards the undersluices for easy disposal. - Protecting the structural integrity of the weir by minimizing the impact of high-velocity flows.
💡Key Conceptual Anchor:Irrigation Engineering
Question 6 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Infiltration is the
Correct Answer: Option C — both (A) and (B)
Detailed Academic Explanation:
Let's understand what Infiltration is in simple terms, especially when we talk about water and soil, like in Irrigation Engineering . Imagine it raining, or you're watering your garden. What happens to the water? Infiltration is essentially how water gets *into* the soil from the ground surface. Let's look at the options: Option B: absorption of water by soil surface This is definitely a part of infiltration! The very first step for water to enter the soil is for the soil's surface to 'soak up' or 'absorb' the water. Think of a sponge soaking up water. This is the starting point of the whole process. Option A: movement of water through the soil Once the water is absorbed by the surface (as explained in Option B), it doesn't just stay right at the top. It starts to move *downward* into the soil's deeper layers, flowing *through* the tiny spaces (pores) between the soil particles. This downward movement into and through the soil is also a crucial part of what we call infiltration. So, infiltration isn't just about the water sitting *on* the surface; it's about it getting *in* and then moving *through* the soil. Therefore, the most complete and correct answer is Option C: both (A) and (B) . Infiltration involves both the initial absorption of water at the soil surface and the subsequent movement of that water downwards through the soil itself. It's a very important concept in Irrigation Engineering because it tells us how much water actually enters the soil to be used by plants, and how much might run off.
💡Key Conceptual Anchor:Irrigation Engineering
Question 7 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A fall which maintains its depth, is
Correct Answer: Option B — A low weir fall
Detailed Academic Explanation:
A fall is a structure constructed across a canal to lower the water level and dissipate surplus energy caused by a difference in bed levels. A low weir fall is specifically designed to maintain the depth of flow in the canal. It allows water to flow smoothly over a broad-crested weir while keeping the upstream depth nearly constant. This type of fall helps in energy dissipation and prevents scouring and erosion downstream by stabilizing the flow conditions. Trapezoidal notch fall and rectangular notch fall are primarily used for measuring discharge and controlling flow rather than maintaining depth. Hence, among the given options, the fall that maintains its depth is the low weir fall . Therefore, the correct answer as per exam and technical standards is Option B: A low weir fall .
💡Key Conceptual Anchor:Irrigation Engineering
Question 8 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For a catchment area of 120 km 2 , the equilibrium discharge in m 3 /hour of an S-curve obtained by the summation of 6 hour unit hydrograph is
Correct Answer: Option A — 0.2 x 106
Detailed Academic Explanation:
The correct answer is Option A: 0.2 x 10 6 The question involves understanding S-curve hydrographs and their relationship to unit hydrographs . An S-curve hydrograph is created by summing an infinite series of unit hydrographs , each lagged by a duration equal to the unit hydrograph duration. In this case, we have a 6-hour unit hydrograph. The equilibrium discharge of the S-curve represents the constant rate of runoff when the rainfall continues indefinitely at a rate of 1 cm (or 1 unit) over the basin for the duration of the unit hydrograph. The equilibrium discharge (Q eq ) is calculated as: Q eq = (Area of catchment x Rainfall depth) / Duration of Unit Hydrograph Where, Area = 120 km 2 = 120 x 10 6 m 2 Rainfall depth = 1 cm = 0.01 m Duration = 6 hours Q eq = (120 x 10 6 m 2 x 0.01 m) / 6 hours Q eq = (1.2 x 10 6 m 3 ) / 6 hours Q eq = 0.2 x 10 6 m 3 /hour Therefore, the equilibrium discharge of the S-curve is 0.2 x 10 6 m 3 /hour .
💡Key Conceptual Anchor:Irrigation Engineering
Question 9 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If the R.L’s of canal bed level and high flood level of drainage are 212.0 m and 210.0 m respectively, then cross drainage work will be
Correct Answer: Option A — aqueduct
Detailed Academic Explanation:
An aqueduct is a type of cross drainage work where the canal passes over the drainage. In this case, the R.L. (Reduced Level) of the canal bed is higher at 212.0 m compared to the high flood level of the drainage at 210.0 m. This difference in levels makes an aqueduct the appropriate structure, allowing the canal to safely cross above the drainage.
💡Key Conceptual Anchor:Irrigation Engineering
Question 10 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The unit hydrograph due to a storm may be obtained by dividing the ordinates of the direct runoff hydrograph by
Correct Answer: Option B — period of storm
Detailed Academic Explanation:
Understanding Unit Hydrographs: Imagine a unit hydrograph as the standard response of a watershed (an area of land where all water drains to a common outlet) to a unit depth of rainfall . It is a tool to predict how a river will react to rainfall. How is the unit hydrograph derived? To derive a unit hydrograph, we isolate the effect of rainfall from the direct runoff hydrograph (DRH) , which shows the flow in a river directly caused by rainfall. What do we divide by? We scale down the DRH to represent the response to a unit depth of rainfall . The steps are: 1. Divide the ordinates of the DRH (values at different times) by the period of the storm . 2. This ensures that the hydrograph ordinates correspond to a unit depth of rainfall excess for the specified duration. Why not the other options? - Direct Runoff Volume: While this shows the total runoff, dividing the DRH by volume does not yield a unit hydrograph. - Total Rainfall: Not all rainfall contributes to runoff; some is lost to infiltration and evaporation. - None of the above: This is incorrect because the correct method is dividing by the storm period. Correct Answer: Option B: Period of Storm
💡Key Conceptual Anchor:Irrigation Engineering
Question 11 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Finally formed berms in canals are provided for
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “Finally formed berms in canals are provided for”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 12 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Canals constructed for draining off water from water logged areas, are known
Correct Answer: Option A — Drains
Detailed Academic Explanation:
Drains is the correct answer to “Canals constructed for draining off water from water logged areas, are known”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 13 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A hydroelectric scheme operating under a head of 80 m will be classified as
Correct Answer: Option C — high head scheme
Detailed Academic Explanation:
high head scheme is the correct answer to “A hydroelectric scheme operating under a head of 80 m will be classified as”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 14 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If d 1 is the depth of cutting, d 2 is the height of the bank from bed level r 2 : 1 and r 1 : 1 are the slopes in filling and cutting respectively, the horizontal distance n between the bed and bank, is
Correct Answer: Option B — x = r2d2
Detailed Academic Explanation:
x = r2d2 is the correct answer to “If d 1 is the depth of cutting, d 2 is the height of the bank from bed level r 2 : 1 and r 1 : 1 are the slopes in filling and cutting respectively, the horizontal distance n between the bed and bank, is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 15 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A minimum of 90 cm free board is provided if the discharge in the canal is between
Correct Answer: Option C — Over 60 cumecs
Detailed Academic Explanation:
Over 60 cumecs is the correct answer to “A minimum of 90 cm free board is provided if the discharge in the canal is between”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 16 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If the irrigation efficiency is 80%, conveyance losses are 20% and the actual depth of watering is 16 cm, the depth of water required at the canal outlet, is
Correct Answer: Option D — 25 cm
Detailed Academic Explanation:
25 cm is the correct answer to “If the irrigation efficiency is 80%, conveyance losses are 20% and the actual depth of watering is 16 cm, the depth of water required at the canal outlet, is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 17 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The structure constructed to allow drainage water to flow under pressure through an inverted syphon below a canal, is called
Correct Answer: Option D — Syphon aqueduct
Detailed Academic Explanation:
Syphon aqueduct is the correct answer to “The structure constructed to allow drainage water to flow under pressure through an inverted syphon below a canal, is called”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 18 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The downstream expansion head of a guide bank is extended to subtend an angle at the centre, equal to
Correct Answer: Option B — 45°
Detailed Academic Explanation:
45° is the correct answer to “The downstream expansion head of a guide bank is extended to subtend an angle at the centre, equal to”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 19 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The uplift pressure on a dam can be controlled by i) constructing cutoff under upstream face ii) constructing drainage channels bet-ween the dam and its foundation iii) by pressure grouting in foundation The corret answer is
Correct Answer: Option D — (i), (ii) and (iii)
Detailed Academic Explanation:
(i), (ii) and (iii) is the correct answer to “The uplift pressure on a dam can be controlled by i) constructing cutoff under upstream face ii) constructing drainage channels bet-ween the dam and its foundation iii) by pressure grouting in foundation The corret answer is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 20 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be
Correct Answer: Option C — $$\frac{1}{{1 - {{0.9}^ \circ }10}}$$
Detailed Academic Explanation:
$$\frac{1}{{1 - {{0.9}^ \circ }10}}$$ is the correct answer to “If the risk of a flood occurring in the next 10 years is accepted to 10%, then the return period for design should be”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 21 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The width of a meander belt is the transverse distance between
Correct Answer: Option A — Apex point of one curve and apex point of the reserve curve
Detailed Academic Explanation:
Apex point of one curve and apex point of the reserve curve is the correct answer to “The width of a meander belt is the transverse distance between”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 22 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The ratio of average values of shear stresses produced on the bed and the banks of a channel due to flowing water is
Correct Answer: Option C — greater than 1
Detailed Academic Explanation:
greater than 1 is the correct answer to “The ratio of average values of shear stresses produced on the bed and the banks of a channel due to flowing water is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 23 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The kor depth for rice is 190 mm and kor period is 14 days. The outlet factor for this will be
Correct Answer: Option A — 637 hectares/m3/sec
Detailed Academic Explanation:
637 hectares/m3/sec is the correct answer to “The kor depth for rice is 190 mm and kor period is 14 days. The outlet factor for this will be”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 24 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The main function of a diversion head works of a canal from a river, is
Correct Answer: Option D — To raise water level
Detailed Academic Explanation:
To raise water level is the correct answer to “The main function of a diversion head works of a canal from a river, is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 25 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The amount of irrigation water required to meet the evapotranspiration needs of the crop during its full growth is called
Correct Answer: Option C — consumptive irrigation requirement
Detailed Academic Explanation:
consumptive irrigation requirement is the correct answer to “The amount of irrigation water required to meet the evapotranspiration needs of the crop during its full growth is called”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 26 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For wave action in dams, the maximum height of freeboard is generally taken to be equal to (where hw is height of wave.)
Correct Answer: Option D — 1.50 hw
Detailed Academic Explanation:
1.50 hw is the correct answer to “For wave action in dams, the maximum height of freeboard is generally taken to be equal to (where hw is height of wave.)”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 27 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The intensity of irrigation means
Correct Answer: Option A — Percentage of culturable commanded area to be irrigated annually
Detailed Academic Explanation:
Percentage of culturable commanded area to be irrigated annually is the correct answer to “The intensity of irrigation means”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 28 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Trap efficiency of a reservoir is a function of
Correct Answer: Option A — capacity/inflow ratio
Detailed Academic Explanation:
capacity/inflow ratio is the correct answer to “Trap efficiency of a reservoir is a function of”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 29 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Seepage through embankments in an earthen dam is controlled by
Correct Answer: Option C — drain trenches
Detailed Academic Explanation:
drain trenches is the correct answer to “Seepage through embankments in an earthen dam is controlled by”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 30 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A river is said to be of
Correct Answer: Option D — All the above
Detailed Academic Explanation:
All the above is the correct answer to “A river is said to be of”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 31 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
An artesian aquifer is the one where
Correct Answer: Option B — water is under pressure between two impervious strata
Detailed Academic Explanation:
water is under pressure between two impervious strata is the correct answer to “An artesian aquifer is the one where”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 32 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
For a unique design of a channel by Kennedy's theory
Correct Answer: Option C — Its breadth and depth ratio must only be known
Detailed Academic Explanation:
Its breadth and depth ratio must only be known is the correct answer to “For a unique design of a channel by Kennedy's theory”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 33 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The scour depth D of a river during flood, may be calculated from the Lacey's equation
Correct Answer: Option C — D = 0.47 $${\left( {\frac{{\text{Q}}}{{\text{f}}}} \right)^{\frac{1}{3}}}$$
Detailed Academic Explanation:
D = 0.47 $${\left( {\frac{{\text{Q}}}{{\text{f}}}} \right)^{\frac{1}{3}}}$$ is the correct answer to “The scour depth D of a river during flood, may be calculated from the Lacey's equation”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 34 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Unit of runoff in M.K.S. system is
Correct Answer: Option A — cubic metre/sec
Detailed Academic Explanation:
cubic metre/sec is the correct answer to “Unit of runoff in M.K.S. system is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 35 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Under the same conditions, which of the following shapes of water surface will give the highest rate of evaporation ?
Correct Answer: Option B — convex water surface
Detailed Academic Explanation:
convex water surface is the correct answer to “Under the same conditions, which of the following shapes of water surface will give the highest rate of evaporation”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 36 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The main cause of meandering is
Correct Answer: Option C — the extra turbulence generated by the excess of river sediment during floods
Detailed Academic Explanation:
the extra turbulence generated by the excess of river sediment during floods is the correct answer to “The main cause of meandering is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 37 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
According to Kennedy, the critical velocity (V 0 ) in meters in a channel is the mean velocity which keeps the channel free from silting or scouring. Its value is given by (where m is critical velocity ratio and D is the depth of the channel).
Correct Answer: Option B — V0 = 0.55 mD0.64
Detailed Academic Explanation:
V0 = 0.55 mD0.64 is the correct answer to “According to Kennedy, the critical velocity (V 0 ) in meters in a channel is the mean velocity which keeps the channel free from silting or scouring. Its value is given by (where m is critical velocity ratio and D is the depth of the channel).”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 38 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
A 70% index of wetness means
Correct Answer: Option B — rain deficiency of 30%
Detailed Academic Explanation:
rain deficiency of 30% is the correct answer to “A 70% index of wetness means”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 39 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
Useful soil moisture for plant growth, is
Correct Answer: Option A — Capillary water
Detailed Academic Explanation:
Capillary water is the correct answer to “Useful soil moisture for plant growth, is”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
Question 40 of 40
★ PPSC SDO
★ FPSC AEE
★ PPSC SDO
★ FPSC AEE
The flow of water after spilling over the weir crest in chute spillway and side channel spillway respectively are
Correct Answer: Option A — At right angle and parallel to weir crest
Detailed Academic Explanation:
At right angle and parallel to weir crest is the correct answer to “The flow of water after spilling over the weir crest in chute spillway and side channel spillway respectively are”. This question is standard in competitive examination syllabi for Irrigation Engineering.
💡Key Conceptual Anchor:Irrigation Engineering
✓Link copied to clipboard
Continue Your Practice
Airport Engineering — Part 1
Master the next curriculum module with 40 exam-standard MCQs.
In competitive commission exams (FPSC, PPSC, KPPSC, SPSC, CSS, PMS), questions are frequently phrased with distractor options designed to catch rote learners. Whenever you answer an MCQ, read the Detailed Academic Explanation and Conceptual Anchor to understand why the remaining options are incorrect.