Introduction To Mining Engineering — Part 1 MCQs with Explanations

Practice high-yield Mining Engineering MCQs on Introduction To Mining Engineering — Part 1 with worked academic solutions for PPSC Mines, KPPSC, FPSC, BPSC.

Questions
40
Difficulty Level
Exam-Level
Target Exams
PPSC Mines, KPPSC, FPSC...
Estimated Time
48 mins
Exam-Level PPSC Mines KPPSC FPSC BPSC
Verified for Commission Syllabus • Oct 14, 2026
40

Verified Practice Questions

Interactive test mode with detailed academic worked solutions

Live Progress | 0/40 answered
✓ 0 correct ✗ 0 wrong 0% score
Question 1 of 40
★ PPSC Mines ★ KPPSC

When the occurrence of mineral (e.g. rare minerals) is randomly distributed in a rock then which of the distribution pattern is statistically followed?

Question 2 of 40
★ PPSC Mines ★ KPPSC

It is very difficult to control shaley roof if coal is not left with the shale why?

Question 3 of 40
★ PPSC Mines ★ KPPSC

In connection with lowering or raising of persons by means of bucket etc. for a shaft exceeding "A" m in depth, there shall be significant cover overhead for protection from things falling down the shaft. A is given by

Question 4 of 40
★ PPSC Mines ★ KPPSC

Match the following: Access Haulage Mineralisation P Shaft 1. Track a. Moderate depth Q Decline 2. Trackless b. Deep seated R Adit 3. Hoisting c. Hillock

Question 5 of 40
★ PPSC Mines ★ KPPSC

A surface mine blast design has 9 holes in a row, each of 8m length and 200mm diameter. The spacing and burden are 6m and 5m respectively. The length of subgrade drilling is 1m and the density of in-situ rock is 2.43 t/m 3 . Considering an explosive density of 0.9 t/rn 3 and stemming length of 2m, the powder factor from the blast in t/kg is

Question 6 of 40
★ PPSC Mines ★ KPPSC

Match the following, for standard diamond rods Specification Outer diameter in mm P. AW p. 34.9 Q. BW q. 44.4 R. EW r. 54.0 S. NW s. 66.7

Question 7 of 40
★ PPSC Mines ★ KPPSC

Select the correct order with respect to the core sizes

Question 8 of 40
★ PPSC Mines ★ KPPSC

Which of the following combination of SDL based mining is expected to give best production and productivity of SDL?

Question 9 of 40
★ PPSC Mines ★ KPPSC

In a mine deploying shovel and dumper, the distance from the crest of the bench to the centre of the dumper including safety berm and clearance is 7.5m, the dumping radius and the cutting radii of the shovel are 15m and 12m respectively. The width of the working bench of the mine in m is

Question 10 of 40
★ PPSC Mines ★ KPPSC

In a room-and-pillar stope, bench blasting is conducted using ANFO having density of 800 kg/m 3 . The specific gravity of rock is 2.5, hole diameter is 100 mm and spacing to burden ratio is 1.3. The charge length of each blast hole is 80% of the hole length. For a desired powder factor of 0.48 kg/tonne, the spacing and burden of the blast pattern in m respectively are

Question 11 of 40
★ PPSC Mines ★ KPPSC

In a mine for one shovel six trucks are assigned. The shovel loading time per truck is 5 min, and truck cycle time 20 min. Calculate the match factor.

Question 12 of 40
★ PPSC Mines ★ KPPSC

The following data are provided for a surface mine to be excavated by a shovel: Production target: 10000 te/shift Available hours per shift: 6 hrs Shovel loading cycles per hour: 10 6 Bank density of the material mined: 2400 kg/m 3 Swing factor at 120° swing: 0.91 Bucket fill factor : 0.64 Utilization of available time: 83% No of working days in a year : 300 No of shifts per day : 3 The size of bucket of the shovel in m 3 is

Question 13 of 40
★ PPSC Mines ★ KPPSC

Which of the following support has maximum linear progress?

Question 14 of 40
★ PPSC Mines ★ KPPSC

Every ladder way used in a mine shall project above the mouth of at least

Question 15 of 40
★ PPSC Mines ★ KPPSC

Which of the following is most difficult in opening up an opencast mine?

Question 16 of 40
★ PPSC Mines ★ KPPSC

In-situ ore of 1.5% Cu got diluted with waste rock of value 0.2% Cu. If the resultant extracted ore has 1.2% Cu. What is the percentage of dilution?

Question 17 of 40
★ PPSC Mines ★ KPPSC

Top slicing is an underhand caving method which is a variation of

Question 18 of 40
★ PPSC Mines ★ KPPSC

The diameter of holes in mm commonly used for ring drilling by drifters in sublevel stoping is between

Question 19 of 40
★ PPSC Mines ★ KPPSC

Friction Clutch is used for

Question 20 of 40
★ PPSC Mines ★ KPPSC

The process that sends sand water mixture in underground coal depillaring district is known as

Question 21 of 40
★ PPSC Mines ★ KPPSC

Which of the following method of mining is only applicable to non-coal mines?

Question 22 of 40
★ PPSC Mines ★ KPPSC

As per CEA 2010, the length of flexible cable used in portable and transportable apparatus shall not be more than

Question 23 of 40
★ PPSC Mines ★ KPPSC

A dragline is required to remove 3,00,000 m 3 of rock per month on the bank volume basis. Consider the following data for the dragline operation. Effective working hours per month = 450 Bucket fill factor = 0.8 Cycle time = 65 s Swell factor of the rock = 1.25 The minimum bucket capacity of the dragline in m 3 is

Question 24 of 40
★ PPSC Mines ★ KPPSC

A shearer is deployed in a mine where the specific energy consumption for cutting coal is 800 kJ/m 3 . The specific gravity of coal is 1.2. If the machine produces 700 te/h, the electrical power consumption in kW of the shearer at 65% motor efficiency is

Question 25 of 40
★ PPSC Mines ★ KPPSC

In an underground coal mine, a freshly exposed roof can be supported by a temporary support in the form of

Question 26 of 40
★ PPSC Mines ★ KPPSC

A bucket wheel excavator with 20 buckets of capacity 0.5 m 3 each, rotates at 5 rev/min. The bucket fill factor is 80%. The excavator loads on to 1200 mm wide belt conveyor. The cross-section area (m 2 ) of the material on the belt is 0.1B 2 , where B is the belt width in m. The minimum speed of the belt in m/s to avoid spillage of material is

Question 27 of 40
★ PPSC Mines ★ KPPSC

An ore block of length 30m and height 20m having an average width of 1.5m with sharp boundary walls is mined with a minimum mining width of 2m. If the tonnage factors are 3 t/m 3 for ore, 2 t/m 3 for wall rock and average grade of ore is 10%, the diluted grade of ore mined in percent is

Question 28 of 40
★ PPSC Mines ★ KPPSC

In an overburden bench of an iron ore mine the following data were found: Height = 10m Burden = 4m Spacing = 3m Sub-grade drilling length = 1m Collar stemming length = 3m If the diameter of the explosive column is 150 mm and the specific gravity of explosive and that of rock are 0.9 and 2.4 respectively, the powder factor in te/kg will be

Question 29 of 40
★ PPSC Mines ★ KPPSC

Cut & Fill stoping can be done by

Question 30 of 40
★ PPSC Mines ★ KPPSC

A flat coal seam of thickness (t) 3m is excavated and broken roof rock has completely filled the space created due to extraction as shown in the figure. If the bulking factor of roof rock is 1.2. the caving height (H) in m is

Question 31 of 40
★ PPSC Mines ★ KPPSC

In the order of the chronological development, the longwall support systems are arranged as P Powered support Q Link bar and friction support R Frame support S Hydraulic support

Question 32 of 40
★ PPSC Mines ★ KPPSC

Water bearance of Indian coal seam is

Question 33 of 40
★ PPSC Mines ★ KPPSC

In any working below ground there should be provided at least two shaft or incline which should be away from each other by a minimum distance

Question 34 of 40
★ PPSC Mines ★ KPPSC

A vertical ore body having a consistent width of 100 m has been excavated by the open pit method up to a depth of 100 m at a pit slope angle of 45°. The figure shows the cross section of the open pit. If the ore body is further excavated by a depth of 10 m, maintaining the same pit slope angle, the ratio of waste rock to ore is

Question 35 of 40
★ PPSC Mines ★ KPPSC

The delay interval in short delay detonator is

Question 36 of 40
★ PPSC Mines ★ KPPSC

What is the name of the media through which coal pulp in hydraulic mining is sent from face to pulp sump or coal crusher?

Question 37 of 40
★ PPSC Mines ★ KPPSC

Shale as immediate roof in underground, coal mine is not suitable because

Question 38 of 40
★ PPSC Mines ★ KPPSC

Blasting of stope in VCR method consists of

Question 39 of 40
★ PPSC Mines ★ KPPSC

Which one of tire following HEMM is a tyre mounted?

Question 40 of 40
★ PPSC Mines ★ KPPSC

In an opencast mine shown in the figure below, the coal has a density of 1.4 t/m 3 . Assuming mining operation started from plane XY, the operating stripping ratio under the given conditions in m 3 /t is

✓ Link copied to clipboard
Continue Your Practice

Coal Mining — Part 1

Master the next curriculum module with 40 exam-standard MCQs.

Next Practice Set →

💡 Examiner's Advisory for Mining Engineering

In competitive commission exams (FPSC, PPSC, KPPSC, SPSC, CSS, PMS), questions are frequently phrased with distractor options designed to catch rote learners. Whenever you answer an MCQ, read the Detailed Academic Explanation and Conceptual Anchor to understand why the remaining options are incorrect.

More Modules in Mining Engineering

View All →
📚

Study Guides

Topic summaries and syllabus breakdown

Explore Guides →
🎯

Complete Library

Search through 78,000+ verified MCQs

Browse Library →
📱

Mobile App

Offline mock tests and instant bookmarks

Get Mobile App →