Mine System Engineering — Part 1 MCQs with Explanations

Practice high-yield Mining Engineering MCQs on Mine System Engineering — Part 1 with worked academic solutions for PPSC Mines, KPPSC, FPSC, BPSC.

Questions
40
Difficulty Level
Exam-Level
Target Exams
PPSC Mines, KPPSC, FPSC...
Estimated Time
48 mins
Exam-Level PPSC Mines KPPSC FPSC BPSC
Verified for Commission Syllabus • Oct 14, 2026
40

Verified Practice Questions

Interactive test mode with detailed academic worked solutions

Live Progress | 0/40 answered
✓ 0 correct ✗ 0 wrong 0% score
Question 1 of 40
★ PPSC Mines ★ KPPSC

Workmen arrive at a mine workshop to receive tools for maintenance. The inter-arrival time of workmen at the service counter is exponentially distributed with an average time of 10 min. The service time at the counter is also distributed exponentially with a mean time of 6 min. The average time spent by a workman waiting for his turn to be served in min is

Question 2 of 40
★ PPSC Mines ★ KPPSC

A mining project is composed of five activities whose three time estimates in months are given below: Activity Estimated duration (months) Optimistic time Most likely time Permissible time 1 - 2 1 1 7 1 - 3 2 5 8 2 - 4 1 1 7 3 - 4 2 5 14 4 - 5 3 6 15 The expected duration of the mining project in months is

Question 3 of 40
★ PPSC Mines ★ KPPSC

The failure data analysis of a longwall mining system consisting of thre major subsystems revealed that the failure rate of shearer, face conveyor any stage loader are 0.15/ hour, 0.2/ hour and 0.1/ hour respectively. If all the subsystems must be running for a satisfactory system operation, the reliability of the longwall system for a period of 4 hours is

Question 4 of 40
★ PPSC Mines ★ KPPSC

Consider the following linear programming problem: Maximize z = 3x + 2y s.t. 3x + 2y ≥ 15 2x + 3y ≤ 6 x ≥ 0, y ≥ 0 The above linear programming problem has

Question 5 of 40
★ PPSC Mines ★ KPPSC

The variance of failure time (time to failure) of an electric motor in shovel is 1600 hr 2 . If the failure time follows an exponential distribution. the expected mean time between failure in hr is

Question 6 of 40
★ PPSC Mines ★ KPPSC

The unit cost of transportation of a balanced transportation problem is shown below: Destination → D1 D2 D3 Supply Source s S1 7 3 6 60 S2 5 4 9 60 S3 8 6 7 80 Demand 50 120 30 The transportation cost of the initial basic feasible solution obtained by the North-West corner rule is

Question 7 of 40
★ PPSC Mines ★ KPPSC

A workshop has four machines for assigning four jobs. Each job can be assigned to only one machine. Estimated processing cost (in Rs.) at each machine to complete each task is given in the table below Machine M1 M2 M3 M4 Tasks T1 61 92 52 72 T2 42 49 69 85 T3 47 59 80 71 T4 65 70 68 72 The minimum value of total processing cost based on an optimal assignment schedules is

Question 8 of 40
★ PPSC Mines ★ KPPSC

The probabilistic nature of activity times in PERT network is described by which one of the following distributions?

Question 9 of 40
★ PPSC Mines ★ KPPSC

A pumping station in a mine has 4 pumps, P 1 , P 2 , P 3 and P 4 which are connected functionally in parallel configuration as shown in the figure. The individual reliability of the pumps P 1 , P 2 , P 3 and P 4 are 0.80, 0.90, 0.85 and 0.95 respectively. For an effective dewatering operation in the mine denoting system success, at least three pumps should be in operation. The reliability of the system is

Question 10 of 40
★ PPSC Mines ★ KPPSC

In an opencast mine, dumpers arrive at a shovel location with an average arrival rate of 12 per/hour. The inter-arrival times of the dumpers follow an exponential distribution. The service times of the shovel also follow an exponential distribution with an average of 3 minute. The average waiting time of a dumper in the queue in minutes is

Question 11 of 40
★ PPSC Mines ★ KPPSC

The feasibility region of an LP problem in variable x and y is given by the following constraints, in addition to the non- negativity constraints. y ≤ 60; x ≤ 90; x + y ≤ 70 The numbers of corner point feasible solutions for this problem are

Question 12 of 40
★ PPSC Mines ★ KPPSC

A project network comprises five activities as shown below. The activity durations. in days. are as indicated. Crashing of any activity costs Rs. 1000 per day. If the project is crashed to the shortest possible duration without changing the critical path the total crashing coso in Rs. is

Question 13 of 40
★ PPSC Mines ★ KPPSC

The failure and the repair rates of a shovel are 0.06 hr-1 and 0.04 hr-1 respectively. The availability of the shovel in percentage is

Question 14 of 40
★ PPSC Mines ★ KPPSC

In a PERT network, the activities on the critical path are a, b and c. The standard deviations of the durations of these activities are 2, 2 and 1 respectively. The variance of the project duration is

Question 15 of 40
★ PPSC Mines ★ KPPSC

A mining machinery company has four plants at locations A, B, C, and D and three warehouses at destinations X, Y and Z. The number of machine units available at the plants A, B, C and Dare 5, 8, 7 and 14 respectively. The demands at X, Y and Z are 7, 9 and 18 respectively. The unit costs of transportation in rupees as follows: Destinations X Y Z Locations A 20 70 40 B 30 30 10 C 50 40 70 D 10 60 20 The total number of basic variables obtained based on the initial basic feasible solution is

Question 16 of 40
★ PPSC Mines ★ KPPSC

The solution of the following system of linear equations is x + 4y + 3z = 0 3x + 5y + 2z = 0 8x + 10y + 12z = 0

Question 17 of 40
★ PPSC Mines ★ KPPSC

In PERT network, the activity duration is assumed to follow

Question 18 of 40
★ PPSC Mines ★ KPPSC

In an opencast mine loading and transporting has been carried out by shovel dumper combination. There is only one shovel is in operation. Dumpers arrive at the rate of 10 dumpers per hour and it takes shovel on an average 5 minutes to load a dumper. Assume arrival is Poisson and service time is exponentially distributed. What is expected idle time of a dumper in the system?

Question 19 of 40
★ PPSC Mines ★ KPPSC

A queue of trucks at a crusher plant hopper is known to be M/M/1 queue. The probability that there is no truck to unload is 0.3. Due to rains the mean service time at the hopper is increased by 30%. As a consequence, the expected number of trucks in the queuing system (including the one possibly unloading) becomes

Question 20 of 40
★ PPSC Mines ★ KPPSC

The time study data of an equipment deployed in a mine during a calendar month is given below. Total working hours = 400 Total maintenance hours = 100 Total hours of actual work = 240 The percentage of utilization of the equipment is

Question 21 of 40
★ PPSC Mines ★ KPPSC

ISO 9000 Quality Systems DO NOT contain

Question 22 of 40
★ PPSC Mines ★ KPPSC

The following project network is given with arrows as activities and the numbers by each arrow representing job durations in days. The network has two dummy activities D 1 and D 2 . The minimum completion time of the project in days is

Question 23 of 40
★ PPSC Mines ★ KPPSC

A balanced transportation problem is characterised by

Question 24 of 40
★ PPSC Mines ★ KPPSC

The feasible region of an LP problem is shown as given below. The maximum value of the objective function Z = 1600X 1 + 1200X 2 is

Question 25 of 40
★ PPSC Mines ★ KPPSC

There are 50 lemon trees in a reclaimed mine area. Each tree produces 800 lemons per year. For each additional tree planted in this area, considering all trees, the output number of fruits per tree drops by 10 lemons in a year. The number of trees that to be added to the existing reclaimed area in order to maximise the total number of lemons in the year is

Question 26 of 40
★ PPSC Mines ★ KPPSC

In industrial work study, work sampling is a technique of

Question 27 of 40
★ PPSC Mines ★ KPPSC

A mining project comprising of A, B and C activities is scheduled for 90 days at a cost of Rs. 1200 million. The manager of the project decides to reduce the time for completion of the project to 85 days. The decision was taken after 45 days, The minimum cost of the project in million rupees after crashing 5 days is

Question 28 of 40
★ PPSC Mines ★ KPPSC

Which one of the following operation research problems is solved by the Branch and Bound algorithm?

Question 29 of 40
★ PPSC Mines ★ KPPSC

In the project network shown activity durations are given in months. If the activity can be crashed to expedite the project, which one would you crash and by how many months?

Question 30 of 40
★ PPSC Mines ★ KPPSC

The failure data of equipment follows an exponential distribution. If the mean time between failure is 3000 hours. the reliability of the equipment for 750 hours is

Question 31 of 40
★ PPSC Mines ★ KPPSC

Four mines A, B, C and D are located along a road as shown with production in Mt per year 1, 2, 1 and 3 respectively. In order to handle total coal produced. the ideal distance of a coal washery along the road from the mine A in Km is

Question 32 of 40
★ PPSC Mines ★ KPPSC

A system of two identical mine pumps were to connected in series has reliability 0.49. If the pumps were to be connected in parallel. the system reliability would be

Question 33 of 40
★ PPSC Mines ★ KPPSC

In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression

Question 34 of 40
★ PPSC Mines ★ KPPSC

A company has three mines at locations A, B and C, which supply coal to power plants at D, E, F and G. Mines A, B and C produce 1800 t/day, 1700 t/day, and 2900 t/day respectively. Daily raw coal requirements at the power plants D, E, F and G from these mines are 2050 t, 1600 t, 1300 t, and 1450 t respectively. Unit transportation costs are as follows: Mines ↓ Power Plants D E F G A 3.5 4.0 2.5 5.5 B 4.5 3.7 6.0 4.7 C 4.2 3.8 5.2 2.9 The company has to minimize the total cost of transportation to the power plants. The problem is

Question 35 of 40
★ PPSC Mines ★ KPPSC

The three time estimates of PERT network are assumed to follow

Question 36 of 40
★ PPSC Mines ★ KPPSC

A system consists of four elements A, B, C and D which are connectec functionally in a parallel configuration. The individual reliability of the elements is 0.80, 0.82, 0.85 and 0.90 respectively. The reliability of the system is

Question 37 of 40
★ PPSC Mines ★ KPPSC

A bunker-conveyor system as shown in the figure works under the following scheme: i. Bunker and two conveyors running ii. Bunker and either of the two conveyors running If the bunker and the two conveyors have identical reliability of 0.9. the system reliability is

Question 38 of 40
★ PPSC Mines ★ KPPSC

For an LP problem, identify the incorrect statement

Question 39 of 40
★ PPSC Mines ★ KPPSC

A mining company has three mines (MI, M2 and M3) that supply coal to three power plants (P1, P2 and P3). The three mines produce 900. 1000 and 1200 te of coal per day respectively. The power plant requirements from these three mines are 1200. 1000 and 900 te per day respectively. The unit cost of transporting coal from the three mines to the three power plants in Rs. is given below Power Plants P1 P2 P3 Mines M1 8 10 12 M2 12 13 12 M3 14 10 11 Based on the initial basic feasible solution, using Vogel's approximation method, the total transportation cost in Rs. is

Question 40 of 40
★ PPSC Mines ★ KPPSC

In an opencast mine with shovel-dumper combination have 1 shovel and 6 dumpers. The reliability of the shovel is 0.9 and all the dumpers have equal reliability of 0.8. What is the system reliability?

✓ Link copied to clipboard
Continue Your Practice

Coal Mining — Part 1

Master the next curriculum module with 40 exam-standard MCQs.

Next Practice Set →

💡 Examiner's Advisory for Mining Engineering

In competitive commission exams (FPSC, PPSC, KPPSC, SPSC, CSS, PMS), questions are frequently phrased with distractor options designed to catch rote learners. Whenever you answer an MCQ, read the Detailed Academic Explanation and Conceptual Anchor to understand why the remaining options are incorrect.

More Modules in Mining Engineering

View All →
📚

Study Guides

Topic summaries and syllabus breakdown

Explore Guides →
🎯

Complete Library

Search through 78,000+ verified MCQs

Browse Library →
📱

Mobile App

Offline mock tests and instant bookmarks

Get Mobile App →